An independent third-party verification shall be conducted in accordance with the following requirements:
- 
        A design review shall be conducted to verify and document compliance with the requirements Section 140.3(a)9, specifically:
- 
                All air barrier components are identified on construction documents
 - 
                All joints, interconnections, and penetrations of the continuous air barrier components are identified on construction documents
 - 
                The continuous air barrier extends on all surfaces of the building envelope (walls, roof, and lowest floor)
 - 
                The continuous air barrier is designed to resist positive and negative pressures from wind, stack effect, and mechanical ventilation.
 - 
                The compliance documents indicate the intent to verify the continuous air barrier by way of on-site visual inspection.
 
 - 
                
 - 
        Inspection shall occur during construction when the continuous air barrier is accessible for a visual inspection. The entire continuous air barrier shall be inspected. The third-party entity conducting the verification shall coordinate with the construction team to schedule site visits such that the entire continuous air barrier is verified.
 - 
        Inspection of the continuous air barrier materials and assemblies shall verify the following are installed correctly:
- 
                Transitions to adjacent air barrier systems – including but not limited to roof parapet transitions, glazed framing systems to adjacent framed wall assemblies’ transitions, plaza waterproofing to podium transitions, vertical wall to soffit transitions
 - 
                Detailing of penetrations through air barrier systems.
 - 
                Building assemblies used as ducts or plenums
 - 
                Contractor internal quality control/quality assurance
 
 - 
                
 
        